Create a Precedence LinkYou can create a precedence constraint between two operations in the Gantt chart.
Create a Start-Start LinkYou can create a start-start synchronization link between two operations in the Gantt chart.
The start-start synchronization link specifies that the two operations must start at the
same time. Create an End-End LinkYou can create an end-end synchronization link between two operations in the Gantt chart.
The end-end synchronization link specifies that the two operations must end at the
same time. Create an End-Start LinkYou can create an end-start synchronization link between two operations in the Gantt chart.
The end-start synchronization link specifies that the first operation must end at the
same time as the second operation starts. You can specify a fixed delay
between the end of the first and the start of the second operation. The Set Delay in Seconds dialog box appears after you select
both operations. A tooltip is displayed with the current delay value, when you move the cursor over the arrow representation in the Gantt chart. After the link is created, you can change the delay by double-clicking the arrow representation of the link in the Gantt chart. |