Creating Time Constraint Links between Operations

You can create time constraint links between operations. These links are either precedence constraints or synchronization links, which are represented by arrows in the Gantt chart.

The creation of constraints between parent objects moves the start/end times of child objects appropriately.

Note that, in addition to the commands described below, you can also drag and drop an operation on to another operation in the Gantt chart to create a constraint.

This task shows you how to:


Before you begin: Open your Gantt chart in a Manufacturing Planning workbench.